Signed a Contract with Saudi Electricity Co. (SEC-EOA), on 30-Dec-2013, for the Construction of 380kV Overhead Transmission Lines for Interconnection of additional Saudi Aramco Co-Generation ... |
30/12/2013 |
|
| 380kV UG Cables - Ashbailyah S/S |
Signed a contract with SEC for the construction of 380kV Underground Cables from New Ashbailyah S/S 9038 to S/S 9015 |
09/10/2013 |
| 380kV UG Cables - Al-Safa BSP |
Signed a contract with SEC-COA, Riyadh for construction of 380kV Underground Cable work associated with connection of Al-Safa BSP |
08/06/2013 |
| Salboukh 380kV BSP |
Signed a contract with Saudi Electricity Co. (SEC-COA), Riyadh for Construction of Salboukh 380/132kV BSP |
28/04/2013 |
| 380kV UG Cables - Doha BSP |
Signed a contract with SEC(EOA) for the Construction of 380kV Underground Cable work associated with Doha 380kV BSP |
23/01/2013 |
| Dhuba Al Bida 380kV OHTL |
Signed a contract with SEC (WOA) for construction of Dhuba - Al Bida 380kV OH Trans. Line |
23/01/2013 |
| 765kV Raichur-Sholapur S/C Trans. Lines for PGCIL |
Signed contracts with Power Grid Corporation of India Ltd., Haryana for the construction of Raichur - Sholapur 765kV Transmission Lines (Part I & II). |
11/04/2012 |
|
Signed a Contract with Saudi Electricity Company on 28/12/2011 for the Construction of 120 MW Open Cycle Power Plant at Tabouk and 180 MW Open ... |
01/01/2012 |